§ 4-54. Submission and review.  


Latest version.
  • (a)

    Content review . Prior to or concurrent with applying for construction plan review, the developer shall submit two copies of the stormwater management plan and report, signed and sealed by a state registered engineer, and supporting data to the building official or the city council's designee for processing. Within five working days of receipt of the stormwater management plan and report, the building official or the city council's designee shall determine whether plans and reports are complete and contain all required information. If a content completeness determination is not made within the required time, the plans and reports shall be deemed complete. The developer shall be notified immediately thereafter of the content completion status of the plan and report. Once the plan and report are determined or deemed complete, the building official or the city council's designee shall accept the plans for technical review.

    (b)

    Technical review.

    (1)

    Once a development application is accepted for technical review, the building official or the city council's designee shall have 60 days for all developments to formulate technical review comments on such development application. The developer shall be notified immediately thereafter of the technical review comments.

    (2)

    The developer shall have 60 days to respond to the technical review comments and submit the requested additional or revised information. Upon request by the developer, an extension of time may be granted by the building official or the city council's designee upon a showing by the developer that a good faith effort is being made to provide the additional or revised information and that additional time is required. In the event a response is not received or an extension obtained, the application shall be considered withdrawn.

    (3)

    Upon receipt of the additional or revised information, the building official, or the city council's designee shall have 30 days to review the additional or revised information. At the end of the timeframe, the building official or the city council's designee shall either finalize his determination or request additional information concerning the response to the technical review comments.

    (4)

    The building official or the city council's designee shall be responsible for approving or disapproving all stormwater management plans and reports involving developments. The building official or the city council's designee shall not approve or recommend approval of any stormwater management plans and reports until said plans and reports satisfactorily comply with this Land Development Code and the comprehensive plan.

    (c)

    Determination factors. Prior to approval or disapproval, the building official or the city council's designee shall determine, for all developments, whether said plans:

    (1)

    Are consistent with this Land Development Code;

    (2)

    Provide design features which address the protection of the public health, safety, and welfare;

    (3)

    Are consistent with the goals, objectives, and policies set forth in the adopted comprehensive plan; and

    (4)

    Provide for necessary public improvements or facilities.

    (d)

    Determinations to ensure compliance. Such determination or recommendation shall be made in writing and shall specify provisions, standards, conditions, or design specifications which must be met in order to ensure compliance with the standards set forth in this Land Development Code and the comprehensive plan.

(Ord. No. 05-536, § 303.05B, 12-20-2005)